220kV GRID STATIONS AND TRANSMISSION LINES
220kV/132kV SHALAMAR SUBSTATION (GIS) AND ALLIED 220KV D/C OVERHEAD TRANSMISSION LINE AND UNDERGROUND CABLE PROJECT (PHASE-I)
Preparation of Layout Plan, Single Line Diagram, Protection Schemes, Preliminary Civil Structure Design, Technical Specifications, Bill of Quantities and Tender Documents.
Total Project Cost – PKR 3,600 Million
Barqaab Share – 100%
Date of Commencement – November 2008
Date of Completion – July 2009
SCOPE OF WORK
3x160MVA, 220/132kV Transformer with Controlling Switchgear on both Sides.
220kV D/C Transmission Line with Line Controlling Equipment for In/Out of one Circuit of Ravi-K.S.K Transmission Line at Shalamar (9KM Long Overhead Transmission Line and 3+3KM underground Cable).
6.3MVA 13/211kV Transformer with Controlling Switchgear for Auxiliary Services.
220kV BAHAWALPUR GRID STATION EXTENSION PROJECT
Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.
Total Project Cost – PKR 309 Million
Barqaab Share – 100%
Date of Commencement – September 2008
Date of Completion – October 2009
SCOPE OF WORK
One No. 220/132kV, 3x160MVA Transformer Bay.
220kV YOUSAFWALA GRID STATION EXTENSION PROJECT
Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.
Total Project Cost – PKR 309 Million
Barqaab Share – 100%
Date of Commencement – September 2008
Date of Completion – September 2009
SCOPE OF WORK
One No. 220/132kV, 3x160MVA Transformer Bay.
220kV HALA ROAD HYDERABAD GRID STATION EXTENSION PROJECT
Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.
Total Project Cost – PKR 309 Million
Barqaab Share – 100%
Date of Commencement – September 2008
Date of Completion – October 2009
SCOPE OF WORK
One No. 220/132kV, 3x160MVA Transformer Bay.
220kV BANNU GRID STATION EXTENSION PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project
Total Project Cost – PKR 309 Million
Barqaab Share – 100%
Date of Commencement – January 2009
SCOPE OF WORK
One No. 220/132kV, 3x160MVA Transformer Bay.
Two Nos. 220kV Line Bays.
220kV LUDEWALA GRID STATION EXTENSION PROJECT
Construction Supervision, Contract Management and Testing & Commissioning for Addition of 3x160MVA 220/132kV Power Transformer Along With 220kv and 132kv Allied Equipment.
Total Project Cost – PKR 309 Million
Barqaab Share – 100%
Date of Commencement – January 2009
Date of Completion – August 2009
SCOPE OF WORK
One No. 220/132kV, 3x160MVA Transformer Bay.
Two Nos. 220kV Line Bays.
220KV CHASHMA – LUDEWALA TRANSMISSION LINE AND EXTENSION OF 220KV LUDEWALA GRID STATION PROJECT
Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document, Evaluation of the Bids, Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – PKR 2,057 Million
Barqaab Share – 100%
Date of Commencement – October 2010
SCOPE OF WORK
170KM long 220kV Double Circuit, Twin Bundle Conductor with OPGW Transmission Line between Chashma and Ludewala.
One Complete Dia (Breaker and a Half Scheme) Comprising Two Line Bays at 220kV Ludewala Substation.
PLC & OPGW Terminal Equipment, SCADA/RTU and Associated Equipment at Chashma-II Substation.
Replacement of PLC Equipment at 220kV Daud Khal Substation.
220kV GAWADAR GIS GRID STATION ALONG WITH ALLIED TRANSMISSINO LINE PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – PKR 2,645 Million
Barqaab Share – 100%
Date of Commencement – January 2011
SCOPE OF WORK
2×250, 220/132kV Auto-Transformer.
2x220kV Dia.
1×6.3MVa, 132/11kV Power Transformer.
6x132kV Line Bays.
72KM 220kV D/C Transmission Line on “Greely” Conductor (Twin Bundle) from Iran Border to Gawadar Grid Station.
220/132kV ROHRI TO SHIKARPUR AND ROHRI TO GAMBAT TRANSMISSION LINE PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – PKR 713 Million
Barqaab Share – 100%
Date of Commencement – January 2009
Date of Completion – June 2011
SCOPE OF WORK
62KM long 220kV Double Circuit Twin bundle Transmission Line from 220kV Rohri Grid Station to 220kV Shikarpur Grid Station.
71KM long 132kV Double Circuit Twin Bundle Transmission Line from 220kV Rohri Grid Station to 132kV Gambat Grid Station.
20KM long 132kV Double Circuit Twin Bundle Transmission Line from 220kV Rohri Grid Station to 132kV Khairpur Grid Station.
220kV D.G KHAN TO LORALAI TRANSMISSION LINE PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – PKR 1,905 Million
Barqaab Share – 100%
Date of Commencement – September 2009
Date of Completion – September 2011
SCOPE OF WORK
Lot-I: 85KM Long 220kv Double Circuit Twin Bundle Transmission Line from D.G Khan Grid Station to 220kV Loralai Grid Station (From D.G. Khan Grid Station to Location No.261).
Lot-II: 85KM Long 220kv Double Circuit Twin Bundle Transmission Line from D.G Khan Grid Station to 220kV Loralai Grid Station (From Location No.261 to Location No.520).
Lot-III: 80KM Long 220kv Double circuit Twin Bundle Transmission Line from D.G Khan Grid Station to 220kV Loralai Grid Station (From Location No.520 to Loralai Grid Station).
220kV LORALAI GRID STATION PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – PKR 2,500 Million
Barqaab Share – 100%
Date of Commencement – January 2011
Date of Completion – June 2012
SCOPE OF WORK
2x250MVA, 220/132kV ATFs
2x220kV Dia.
6x132kV L/Bays.
1×10/13MVA, 132/11kV PTF.
3x132kV T/Bays.
220kV ROHRI AND SHIKARPUR GRID STATION EXTENSION PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – RMP 60 Millions PKR 177 Millions
Barqaab Share – 100%
Date of Commencement – May 2010
Date of Completion – December 2011
SCOPE OF WORK
220kV Rohri Grid Station
220kV Equipment (One and a Half Breaker Scheme)
Two Nos. Transformer Bays with 220kV MVA 220/132kV Transformers along with Allied Equipment.
Four (04) Nos. Line Bay.
Two No. Power Transformer Bay.
Telecommunication, SCADA, Protection, Control Metering and Associated Foundations (Civil Works).
132kV Equipment
Six 132kV Line Bays.
Two Nos. Transformer Bays.
Telecommunication, Protection, Control Metering and Associated Foundations (Civil Works).
Two (02) Nos. Power Transformer Bay.
One (01) No. Bus Coupler Bay.
One No. Auxiliary Transformer Bay with 6.3 MVA, 132kV/11kV Auxiliary Transformer along with Allied Equipment.
220kV Shikarpur Grid Station
220kV Equipment (One and a Half Breaker Scheme)
Two (02) Nos. 220kV Line Bays.
Bus bar works (extension) in order to accommodate one dia.
Telecommunication, SCADA, Protection, Control Metering and Associated Foundations (Civil Works).
Associated Civil Works Foundations, Trenches, Walk way etc.
220kV CHISHTIAN GRID STATION AND ASSOCIATED TRANSMISSION LINE PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – PKR 2,633 Millions
Barqaab Share – 100%
Date of Commencement – October 2010
Date of Completion – January 2012
SCOPE OF WORK
2x160MVA, 220/132kV ATF.
2x220kV Dia.
1×6.3MVA, 132/11kV PTF.
6x132kV Line Bays.
Associated Civil Works Foundations, Trenches, Walk way etc.
220kV AIS GRID STATION AT KASSOWAL AND ASSOCIATED TRANSMISSION LINES
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – RMB 55 Millions + PKR 365 Millions
Barqaab Share – 100%
Date of Commencement – February 2010
Date of Completion – March 2012
SCOPE OF WORK
Lot-I
Kassowal 220 kV Grid Station:
2 x 160 MVA, 220/132kV auto-transformers.
4 x 220kV line bays, 2 x 220kV transformer bays, 6 x 132kV line bays and 2 x 132kV transformer bays.
1 x 6.3 MVA, 132/11.5kV power transformer with controlling switchgear at 132kV side.
Control house building.
132kV relay building.
Lot-II
Two Twin Bundle, Double Circuit T/Lines for In & Out of Existing 220kV Vehari-Yousafwala D/C T/Line.
220 kV KHUZDAR – DADU TRANSMISSION LINE AND EXTENSION OF GRIDSTATION AT BOTH ENDS AS A JOINT VENTURE PARTNER WITH NESPAK
Preparation of Bid Level Design, Bill of quantities, Technical Specifications, Tender Document, Evaluation of the Bids, Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
SCOPE OF WORK
300KM long 220kV Double Circuit Dadu-Khuzdar Transmission Line.
2x160MVA Auto Transformer with interfacing to existing 132kV Busbar at Khuzdar Grid Station.
Two 220kV Line Bays at Khuzdar Grid Station.
220kV WAPDA TOWN, LAHORE GRID STATION AND ALLIED TRANSMISSION LINE PROJECT
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project. Working as Joint Venture Partner with NESPAK.
Total Project Cost – PKR 470 Million
Barqaab Share – 100%
Date of Commencement – January 2009
Date of Completion – June 2010
SCOPE OF WORK
220kV GIS Plant with allied Transformer and Line Bays.
3x160MVA Transformers.
20KM long 220kV D/C Transmission Line.
Associated Civil Works Foundations, Trenches, Walk way etc.
220kV/132kV SHALAMAR SUBSTATION (GIS) AND ALLIED 220kV D/C OVERHEAD TRANSMISSION LINE AND UNDERGROUND CABLE PROJECT (PHASE-II)
Residency Construction Supervision including Contract Administration, Quality Control, Contractors Claim Certification, Safety Programme, follow up and Revision of Construction Schedules, Monitoring and Reporting of Progress, Variation Orders and Design Changes during execution, Testing And Commissioning, Final Completion Report and Handing of Over The Project.
Total Project Cost – PKR 3600 Million
Barqaab Share – 100%
Date of Commencement – May 2010
Date of Completion – June 2012
SCOPE OF WORK
3x160MVA, 220/132kV Transformer with Controlling Switchgear on both Sides.
220kV D/C Transmission Line with Line Controlling Equipment for In/Out of one Circuit of Ravi-K.S.K Transmission Line at Shalamar (9KM Long Overhead Transmission Line and 3+3KM underground Cable).
6.3MVA 13/211kV Transformer with Controlling Switchgear for Auxiliary Services.